Royal dockyard infrastructure portfolio: business case and controls

A royal dockyard infrastructure portfolio needed credible baselines for two major programmes of works and a business case covering a decade of investment. We developed the baselines, the Strategic Outline Business Case and the supporting controls.

£500m

Approximate value of the critical facilities portfolio

  • Portfolio

At a glance

Sector
Defence
Scope
Two major programmes of works
Business case
Strategic Outline Business Case
Investment period
Ten years

Problem

A portfolio of infrastructure works at a royal dockyard needed credible baseline programmes to support contract engagement with the MoD for two major programmes of works, and a business case covering a decade of investment.

Intervention

We mobilised a programme management and controls team to develop realistic and credible baselines and the supporting controls infrastructure.

Outcomes

  • Developed the Strategic Outline Business Case including all major programme controls artefacts (probabilistic schedule, resource estimate, QSRA and QCRA) for a portfolio of critical facilities worth approximately £500m over ten years
  • Established a robust and simple programme management and controls reporting suite (Visual Factory) in the main project office, integrating schedule, cost, quality, resourcing and safety data
  • That reporting suite became the forerunner and template for the wider PMO Power BI reporting suite
Illustrative visual of a naval dockyard infrastructure complex with dry docks and engineering halls

Client names are withheld in line with our confidentiality obligations. We are happy to discuss detail directly.