Net-zero energy

Hydrogen pipeline programme: recovery and re-baseline

On a national infrastructure-scale hydrogen programme in FEED, the contractor was struggling to meet its programme controls requirements. We re-baselined a fully integrated programme, achieving a client-approved baseline within six weeks.

6weeks

From engagement to a client-approved baseline

  • National infrastructure

At a glance

Sector
Net-zero energy
Stage
FEED
Scale
National infrastructure
Partner
Tier 1 contractor

Problem

A national infrastructure-scale hydrogen programme in FEED was not set up to support the forward programme. The contractor was struggling to meet contractual requirements for programme controls and scheduling outputs, and to manage key sub-contractors effectively.

Intervention

We partnered with a tier 1 contractor supporting a strategic pipeline partner, providing programme management, controls and commercial management support in an event recovery scenario.

Outcomes

  • Revised, reviewed and re-baselined a fully integrated programme, achieving a client-approved baseline within six weeks of engagement
  • Captured all costs and resources required to deliver the FEED phase and every DCO and consenting deliverable
  • Subsequently engaged to support the domestic and industrial sub-programmes in preparation for the EPC phase
Illustrative visual of hydrogen pipeline infrastructure and above-ground installations

Client names are withheld in line with our confidentiality obligations. We are happy to discuss detail directly.

Get in touch

Speak to a director about your project.

Whether it is a programme to establish, a recovery to lead, a claim to assess, a bid to win or a team to develop, start with a conversation with one of our directors.