Advanced nuclear
Advanced Modular Reactor prototype: programme controls
We provided programme management and controls for a full-scale mock-up of a reactor primary system, spanning multiple suppliers, under strict innovation-funding reporting. The mock-up was delivered on time and below budget.
At a glance
- Sector
- Advanced nuclear
- Scope
- Full-scale reactor primary system mock-up
- Partner
- Tier 1 contractor and AMR consortium partner
- Funding
- ISCF and HMG innovation funding
Problem
The development and manufacture of a full-scale mock-up of a reactor primary system spanned multiple suppliers and contractors, under strict innovation-funding reporting requirements.
Intervention
We partnered with a tier 1 contractor and AMR consortium partner, providing specialist programme management and controls support across the whole programme.
Outcomes
- Established, developed and managed a fully integrated project and programme level schedule spanning every facet of the programme, across multiple suppliers and contractors
- Managed and controlled actual costs and their alignment to key scope elements, satisfying strict Industrial Strategy Challenge Fund and HMG innovation funding reporting requirements
- The full-scale mock-up was delivered on time and below budget

Client names are withheld in line with our confidentiality obligations. We are happy to discuss detail directly.
Related
Related services and sector
AI-enabled delivery
AI-enabled delivery
Get in touch
Speak to a director about your project.
Whether it is a programme to establish, a recovery to lead, a claim to assess, a bid to win or a team to develop, start with a conversation with one of our directors.